Allotment
of plots upto 2 acres, excepting under "Off-the-Shelf" Scheme
shall be made by the Allotment Committee consisting of the
following:
- Director
of Industries, Punjab Chairman.
- Managing
Director/PSIEC.
- Managing
Director/PSIDC
- Managing
Director/PFC
- Chairman/Member
Secretary/PPCB
- Heads
of the Sub-Groups
-
Industrial Adviser-Cum-Additional Director of Industries.
-
Nominee of the developing Agency Member Secretary.
The
recommendations of the Sub-Group/s shall be placed before
the Allotment Committee for consideration and making allotments.
The decision of the Allotment Committee on applications for
allotment of plots shall be final and no appeal shall lie
against it . The Allotment Committee would meet as and when
required and devise its own procedure for conducting the business.
Issuance
of Letter of Intent (LOI)
The developing agency will issue Letter
Of Intent (LOI) to the allottee/s, incorporating therein among
other conditions that the LOI holder will be required to get
the project appraised regarding techno-economic feasibility
form financial institution, scheduled commercial banks or
other public sector consultants and submit the appraisal report
to developing agency within three months of issue of LOI.
The developing agency will hand over possession of land to
the allottee on submission of appraisal report.
The
LOI holder will be required to deposit additional 30% of the
cost of plot within 45 days from the date of issue of LOI.
The allottee will be required to complete the following additional
formalities within a period of twelve months from the date
of possession:
- Obtain
provisional registration of his unit from the concerned
GM/DIC or SIA registration as applicable.
- Submit
building plans/drawings for scrutiny.
- Obtain
consent of financial institution/bank to advance loan for
the proposed project
- In
case of self financing, submit proof of own sources
- Obtain
NOC/consent to establish from PPCB
- Make
application for power /electric connection
In
case an entrepreneur fails to complete the above formalities
within the prescribed period of twelve months, he can apply,
for seeking extension of LOI for additional six months, to
the developing agency, provided , he has taken partial effective
steps. However, another special extension of LOI for six months
can be considered by the developing agency upon payment of
extension fee @ 2.5% of the cost of plot in exceptional cases.
No further extension shall be allowed under any circumstances.
|